Getting Started with the PostgreSQL extension for VS Code
https://marketplace.visualstudio.com/items?itemName=ckolkman.vscode-postgres How to use the extension to connect to your local postgres database.
Once you have the PostgresQl extension installed, you’ll see this little elephant appears at the bottom of your toolbar. When you select that, you’ll be able to add a new database connection by clicking the plus icon here.
This will start a series of prompts that you can fill out to describe the attributes of the database that you’re going to connect to:
1. First, you’ll see the hostname, which in our case we’ll want to be localhost
2. Next, we’ll be asked for the PostgreSQL username we want to authenticate as. In my case, I’m using the username that corresponds to my computer’s user account. This is the user that the Mac Postgres app configures by default. Whatever username you’ve created within Postgres is what you’ll fill in here.
3. After that you’ll be prompted to enter the password for that user’s account. In my case, this is blank and works because the user that is automatically created when you install Postgres will have a username matching your computer’s user account doesn’t have a password by default. In order to set a password for a user account, you’ll need to log in to the Postgres command line application using the `Postgres` user (also with no password) and change the password using a SQL query.
4. Next, the port number (defaults to 5432 but can sometimes be 5433 on WSL for example)
5. You’ll be asked to choose between Use Secure Connection and Standard Connection. When we’re connecting to a remote database (which we can also do from this extension) we’ll want to use a secure connection, but since we’re connecting to our local db here on a private network, using a Standard connection is fine
6. Now, we’re prompted to choose which database we want to display here. If we select Show All Databases then we’ll get to see all Postgres databases that have been created by our user account on our machine. We can also add connections one at a time if we only want to show the databases related to this application, for example. (This means we won’t have to go in and open connections to databases manually every time like we did with the sqlite explorer)
7. Finally, we’re asked to name the database connection we’re creating. This is the name that will show up when we click on the elephant in the sidebar so we can access databases related to this database connection. I’m going to choose localhost databases here just in case I want to add connections to remote databases later on.
After we’ve gone through those steps, we’ll see localhost databases appear within the sidebar. We’re able to collapse and expand these databases to view the tables, columns and types, but we don’t have that play button anymore to click on to see the tables. Instead, we can ctrl+click on one of the tables to see a context menu with some options that we can choose:
1. We can choose Select 'Run select top 1000' and that will give us a table within VSCode that shows the top 1000 rows in that table. unlike the Sqlite extension, however, we can have multiple windows open at once, allowing us to view the contents of multiple tables at the same time if we use a split screen within the workspace.
Что делает видео по-настоящему запоминающимся? Наверное, та самая атмосфера, которая заставляет забыть о времени. Когда вы заходите на RUVIDEO, чтобы посмотреть онлайн «Getting Started with the PostgreSQL extension for VS Code», вы рассчитываете на нечто большее, чем просто загрузку плеера. И мы это понимаем. Контент такого уровня заслуживает того, чтобы его смотрели в HD 1080, без дрожания картинки и бесконечного буферизации.
Честно говоря, Rutube сегодня — это кладезь уникальных находок, которые часто теряются в общем шуме. Мы же вытаскиваем на поверхность самое интересное. Будь то динамичный экшн, глубокий разбор темы от любимого автора или просто уютное видео для настроения — всё это доступно здесь бесплатно и без лишних формальностей. Никаких «заполните анкету, чтобы продолжить». Только вы, ваш экран и качественный поток.
Если вас зацепило это видео, не забудьте взглянуть на похожие материалы в блоке справа. Мы откалибровали наши алгоритмы так, чтобы они подбирали контент не просто «по тегам», а по настроению и смыслу. Ведь в конечном итоге, онлайн-кинотеатр — это не склад файлов, а место, где каждый вечер можно найти свою историю. Приятного вам отдыха на RUVIDEO!
Видео взято из открытых источников Rutube. Если вы правообладатель, обратитесь к первоисточнику.